NUMBER GS-12-500 TYPE PRODUCT SPECIFICATION
TITLE PAGE REVISION
Universal Contact
8 of 9 J
AUTHORIZED BY DATE
ndy Lu 11-Sept-14
CLASSIFICATION
UNRESTRICTED
Copyright FCI.
Form E-3701 – Revision C
GS-01-029
9.3 Acceptance
9.3.1 Electrical and mechanical requirements placed on test samples as indicated in paragraphs 6.0
and 7.0 shall be established from test data using appropriate statistical techniques or shall otherwise
be customer specified, and all samples tested in accordance with this product specification shall meet
the stated requirements.
9.3.2 Failures attributed to equipment, test setup, or operator error shall not disqualify the product. If
product failure occurs, corrective action shall be taken and samples resubmitted for qualification.
9.4 Qualification Testing
Qualification testing shall be performed on sample units produced with equipment and procedures
normally used in production. The test sequences shall be as shown in the qualification test table. Data
shall be provided with the samples noting production history: production lot codes for components and
assemblies, components and assemblies produced to print revision, verification of plating composition
and thickness, etc.
9.5 Re-Qualification Testing
If any of the following conditions occur, the responsible product engineer shall initiate requalification
testing consisting of all applicable parts of the qualification test matrix.
a. A significant design change is made to the existing product which impacts the product form, fit or
function. Examples of significant changes shall include, but not be limited to, changes in the plating
material composition or thickness, contact force, contact surface geometry, insulator design, contact
base material, or contact lubrication requirements.
b. A significant change is made to the manufacturing process which impacts the product form, fit or
function.
c. A significant event occurs during production or end use requiring corrective action to be taken
relative to the product design or manufacturing process.
9.6 Qualification Test Table and Sample Quantity.
Test Items Test
method
TEST SEQUENCE
Group1 Group2 Group3 Group4
Examination of product 1,6 1,5 1,6 1,3
Contact Resistance 6.1 2,5 2,4 2,5
Normal force 7.1 3
Durability 7.2 4
Salt Spray 8.3 3
Thermal Shock 8.1 3
Humidity 8.2 4
Solderability test 8.4 2
Sample Quantity 5 5 5 5
10.0 PACKAGING SPECIFICATION
Refer to FCI specification GS-14-1216.
PDS: Rev :J STATUS:Released Printed: Sep 15, 2014