QUICK START GUIDE FOR DEMONSTRATION CIRCUIT 916
LOW NOISE REGULATED CHARGE PUMP IN 2X2 DFN
2
QUICK START PROCEDURE
Demonstration circuit 916 is easy to set up to evalu-
ate the performance of the LTC3204B-5 and
LTC3204B-3.3. Refer to Figure 1 for proper meas-
urement equipment setup and follow the procedure
below:
NOTE:
When measuring the input or output voltage
ripple, care must be taken to avoid a long ground lead
on the oscilloscope probe. Measure the input or out-
put voltage ripple by touching the probe tip directly
across the V
IN
or V
OUT
and GND terminals. See
Figure 2 for proper scope probe technique
.
1.
Place jumpers in the following positions:
ON
2.
With power off, connect the input power supply to
V
IN
and GND terminals.
3.
Connect the load between V
OUT
and GND terminals.
4.
Turn on the power at the input.
NOTE:
Make sure that the input voltage does not ex-
ceed 5.5V for DC916A-A or 4.5V for DC916A-B. To
prevent input voltage overshoot when the circuit is
connected to a live supply, an aluminum electro-
lytic capacitor can be added to bypass the V
IN
at
the input terminals. See Linear Technology Applica-
tion Note 88 for a complete discussion.
5.
Check for the proper output voltages. V
OUT
= 4.8V
to 5.2V for DC916A-A, V
OUT
= 3.168V to 3.432V for
DC916A-B
NOTE:
If there is no output, temporarily disconnect
the load to make sure that the load is not set too
high.
6.
Once the proper output voltages are established,
adjust the loads within the operating range and ob-
serve the output voltage regulation, ripple voltage,
efficiency and other parameters.
Figure 1.
Proper Measurement Equipment Setup
Figure 2.
Measuring Input or Output Ripple